Welcome to Creekside Subdivision $179,000 All homes have been sold.
The homes at Creekside Subdivision fall under South Dakota Housing guidelines. They were for sale to those who qualify through Meade County Housing. Certain restrictions apply. They can not be used as rentals, they must be owner-occupied. If they are sold within 5-years, all equity is surrendered. These homes do not contain a stove, refrigerator, dish wash, or washer/dryers. Homes are now listed for sale.
UPDATES:
January 6, 2020: Homes are now listed for sale at $179,000. Contact Krysti Schultz at the Realestate Center for information about purchasing 490-2638. Take a virtual tour!
October 17, 2019: Contractors are currently working on garages. A floorplan is available here, however, these homes do not have basements so the area indicating stairs is not applicable. Homes may be ready for sale by December 1, 2019.
May 20, 2019: The City requested re-zoning of five the lots in the Creekside Subdivision from Park Land to Medium Density Residential (4 lots) and the final lot to be rezoned RV/Campground. City Council Presentation. The request resulted in rezoning of 4 of 5 lots to residential and leaving the 5th lot (#5) as Park Land.
March, 2019: The contractor finished the storm sewer and water line construction. He also worked on cleaning up the area. Construction on the curb and gutter and asphalt will happen later in May or June. The contractor is ahead of schedule.
In 2018, the City began planning the development of a small parcel of City-owned land located along the Bear Butte Drainage.
The undeveloped land, located on Woodland Drive, consists of approximately 1.25 acres.
The property location is outside the 100-year floodplain.
The goal was to re-parcel the lot into four single-family, work-force housing units. The lots will each have one Governor's Home with a garage.
These homes will be sold to qualified home-buyers through the SD Governor's Home Program. Tif District and Project Plan presented at the April 16 City Council meeting: Council Report. Audio File.
Timeline:
A public meeting was held in November of 2018 to answer questions and take public comment.
Asphalt & sanitary sewer hookups - completed.
Bids for new water lines and storm sewer. North Star Construction has completed the underground construction. Curb and Gutter construction will happen later this spring. Asphalt will be a month after the curb and gutter is poured. The project is significantly ahead of July 12 finished schedule.
Re-plat into four individual lots.
Homes arrive for installation - August 2019
Ready for sale/occupancy - late September/October 2019.
Pre-existing vacant lot along Woodland Drive.
Draft - lot layout.
Sample image of Governors Home.